Civic Atlas · Federal City
The President's House
How it was built, 1792 to 1829
The stages of the work, the supplies and their prices, the money, and the men who did the labor, from the Commissioners' records and the Treasury accounts at the National Archives, checked against the newspapers of the day.
1 · The house through time
Seven stages, 1792 to 1829
The house went up in stages: walls, roof, finishing, a fire, and a rebuilding. Each stage below gives what happened and how many entries about the house survive in the archive records for those years.
- 1792–1795Foundations and walls
Corner stone laid on October 13, 1792. Foundations dug and the freestone walls begun; one story high by September 1793.
418 entries in the archive records - 1796–1797Walls, roof and shell
Walls carried up and the roof framed. Hoban's first estimate of the cost to finish, November 1797.
555 entries in the archive records - 1798–1800Interior finishing
West end roofed in slate by July 1798. Plastering and joinery priced room by room in September 1799. Small jobs still open in November 1800.
293 entries in the archive records - 1801–1813Lived in
Lived in before it was finished (1804 report). Congress votes money for repairs and improvements in 1807 and 1810.
22 entries in the archive records - 1814Burned
Burned by British troops in August 1814. Interior gone, walls standing (Hadfield's report, October 13, 1814).
5 entries in the archive records - 1815–1817Rebuilt after the fire
Hoban rebuilds: a new roof and floors, mahogany doors. Interior decoration under way in December 1817.
49 entries in the archive records - 1818–1829Finishing, offices and porticoes
Offices, north wall and gates, 1818 to 1820. South portico finished in 1823. Known so far from the newspapers.
Newspapers only so far
How often the house appears in the records, year by year
An entry is one line or page read from a photograph of the records that names the house: a ledger line, a voucher, a letter, an estimate. It is not one payment. Dotted lines mark the start of each stage. 1,391 entries in all, read so far from Record Groups 42 and 217.
The principal floor, with Hoban's room sizes
Room sizes are Hoban's, from his estimate of September 10, 1799 (RG 42, Entry 17, vol. 1, National Archives, Washington, D.C.). The survey shows the same walls today, so the Blue, Red and Green Rooms, the East Room and the halls can be placed. Small rooms: no. 6 room, 14 × 18 ft; no. 7 staircase, 14 × 9 ft; no. 9 staircase, 14 × 28 ft.
Key events
Each event was checked by hand against the record or the newspaper page named under it.
- 1792Archive recordFirst corner stone laid
Laid at the south-west corner on October 13, 1792, with Commissioners Stuart and Carroll, James Hoban and Collen Williamson present.
Proceedings of the Commissioners, vol. 1, MS pp. 144–145. Record Group 42 (Entry 21), National Archives, Washington, D.C. - 1792NewspaperDesign competition
The Commissioners offer a premium for the most approved plan for a President's house, to be produced by July 15, 1792.
National Gazette (Philadelphia), April 2, 1792, p. 4. Library of Congress, Chronicling America. See the page - 1793NewspaperBuilding progress
The President's house is built one story high; upwards of 820 artists and mechanics are employed in building the city.
Gazette of the United States (from Norfolk, August 28), September 7, 1793, p. 2. Library of Congress, Chronicling America. See the page - 1794NewspaperBuilding progress
Letters say the President's house was nearly completed and the Capitol just covering in; bricklayers, carpenters and blacksmiths so wanted that enormous wages were given. (An over-hopeful report: the house was not finished until 1800.)
Gazette of the United States, October 27, 1794, p. 2. Library of Congress, Chronicling America. See the page - 1797Archive recordHoban's first finishing estimate
November 20–23, 1797: the cost to finish the house, £19,874.4.8 ($51,783.29).
RG 42, Entry 17, vol. 1, author's photographs 20230425_100641, 20230425_100732. Record Group 42, Estimates and Proposals (Entry 17, NAID 3023663), National Archives, Washington, D.C. - 1797Archive recordMahogany doors
A Treasury folder is titled “Workmen making Mahogany Doors, April-May 1797”. Only the title has been read.
RG 217, President's House folder title. Record Group 217, National Archives, Washington, D.C. - 1798NewspaperBuilding progress
The roof of the west end of the President's house is covered with slate; preparations are making for covering the remainder.
New Hampshire Gazette (letter from Georgetown, July 17), August 7, 1798, p. 3. Library of Congress, Chronicling America. See the page - 1799Archive recordThe 23-room finishing plan
September 10, 1799: five sheets pricing every room, £12,180.4.3 ($32,400.57).
RG 42, Entry 17, vol. 1, author's photographs 20230425_101517 to 101649. Record Group 42, Estimates and Proposals (Entry 17, NAID 3023663), National Archives, Washington, D.C. - 1799Archive recordCross Hall plaster and cornice
The passage is 19 x 79 ft: 166 sq yd of ceiling, 305 sq yd of walls, 196 ft of cornice with a 1 ft 8 in girt at 7s 6d a foot.
RG 42, Entry 17, vol. 1, author's photograph 20230425_101609. Record Group 42, Estimates and Proposals (Entry 17, NAID 3023663), National Archives, Washington, D.C. - 1799Archive recordHall and passage columns
“Finishing Hall and Passage Columns Capitols &c”, £378.
RG 42, Entry 17, vol. 1, September 10, 1799. Record Group 42, Estimates and Proposals (Entry 17, NAID 3023663), National Archives, Washington, D.C. - 1799Archive recordDoor frontispieces and archways
“Frontispieces to Doors, and Archways to dining room & Stairs”, £429.
RG 42, Entry 17, vol. 1, September 10, 1799. Record Group 42, Estimates and Proposals (Entry 17, NAID 3023663), National Archives, Washington, D.C. - 1800Archive recordSmall jobs left, bells to hang
November 15–16, 1800: letters say several small jobs remain unfinished, and a Baltimore man is asked to come and hang the bells.
RG 42, Entry 17, vol. 1, November 15–18, 1800. Record Group 42, Estimates and Proposals (Entry 17, NAID 3023663), National Archives, Washington, D.C.
Show the other 21 events, 1800 to 1824
- 1800NewspaperFurnishing
Congress debates $15,000 to furnish the President's house; the furniture in Philadelphia is to be sold.
The Republican ledger (Portsmouth, N.H.), April 30, 1800, p. 1. Library of Congress, Chronicling America. See the page - 1801NewspaperBuilding practice
The architects of the public buildings set pine "wooden bricks" in the walls to nail the woodwork to; behind a chimney they are a fire danger.
New Hampshire Gazette, February 17, 1801, p. 3. Library of Congress, Chronicling America. See the page - 1804NewspaperRepairs and improvements
$11,928.29 spent on the President's house in 1804. The house was inhabited before it was finished and still lacks many accommodations thought indispensable in a private citizen's dwelling.
Enquirer (Richmond), Latrobe's report for 1804, December 25, 1804, p. 4. Library of Congress, Chronicling America. See the page - 1807NewspaperMoney voted
For repairs and improvements of the President's house and the ground on which it stands, $15,000.
New Hampshire Gazette (Act of Congress), July 21, 1807, p. 1. Library of Congress, Chronicling America. See the page - 1810NewspaperMoney voted
For repairs to the President's house and offices, $5,000.
Virginia Argus (Act of Congress), May 29, 1810, p. 1. Library of Congress, Chronicling America. See the page - 1814Archive recordBurned: interior gone, walls stand
George Hadfield's report of October 13, 1814 on the public buildings destroyed by fire: the Executive Mansion's interior burnt, its walls standing.
RG 42, Entry 17, vol. 1, author's photographs 20230425_102109–102110 (later copy). Record Group 42, Estimates and Proposals (Entry 17, NAID 3023663), National Archives, Washington, D.C. - 1814NewspaperRepairs and improvements
The House debates the bill making an appropriation for repairs to the President's house.
Daily National Intelligencer, April 19, 1814, p. 3. Library of Congress, Chronicling America. See the page - 1814NewspaperFire and ruin
Letter of August 25: all the public buildings in Washington except the President's house are burnt; the enemy had not yet fired it at 10 o'clock.
Enquirer (Richmond), August 27, 1814, p. 3. Library of Congress, Chronicling America. See the page - 1815Archive recordNew roof and floors
Hoban's 1815 bills: roof scantling, 84,011 ft of naked flooring, and plank.
RG 42, Entry 17, vol. 1, author's photographs 20230425_102546 to 102908. Record Group 42, Estimates and Proposals (Entry 17, NAID 3023663), National Archives, Washington, D.C. - 1815Archive recordMahogany doors with satinwood
St. Domingo mahogany doors 2⅜ in thick, satinwood veneers, ebony beads and paterae; yellow pine plank 20 ft x 6 in x 5/4 in for floors.
RG 42, Entry 17, vol. 1, 1815 bills. Record Group 42, Estimates and Proposals (Entry 17, NAID 3023663), National Archives, Washington, D.C. - 1815NewspaperFire and ruin
A British officer writes that they "burnt the President's Palace" and the Capitol.
Kentucky Gazette (British letter reprinted), January 2, 1815, p. 2. Library of Congress, Chronicling America. See the page - 1815NewspaperMoney voted
Debate on a loan for rebuilding or repairing the Capitol, President's House and offices on their present sites; a motion to strike out the President's house.
Daily National Intelligencer, February 8, 1815, p. 2. Library of Congress, Chronicling America. See the page - 1816NewspaperBuilding progress
The Commissioners choose the men who built these edifices: Latrobe for the Capitol and James Hoban for the President's House; sculptured ornaments of statuary marble to be got in Italy.
Daily National Intelligencer, May 6, 1816, p. 2. Library of Congress, Chronicling America. See the page - 1817NewspaperBuilding progress
The interior decoration of the President's house goes on with despatch; in a few days some principal apartments will be completed; mirrors, carpets and furniture said to be splendid.
Portland Gazette, December 30, 1817, p. 4. Library of Congress, Chronicling America. See the page - 1818NewspaperMoney voted
For finishing the President's House $15,214; offices to the President's House $7,000; the wall north of the house with gates and railing; furnishing $20,000 and a $10,000 deficiency. (One reprint, N.H. Gazette June 9, 1818, reads sixteen thousand two hundred and fourteen.)
Daily National Intelligencer (Act of Congress), April 7, 1818, p. 3. Library of Congress, Chronicling America. See the page - 1819NewspaperBuilding progress
The foundation of the south portico has been laid and it ought to be finished.
Daily National Intelligencer (committee report), January 15, 1819, p. 2. Library of Congress, Chronicling America. See the page - 1820NewspaperBuilding progress
West offices: brick walls carried up, roof covered with copper, a colonnade of six Tuscan columns. North gates and railing: granite pedestal done, cut stone coping and piers, iron gates and railing put up.
Daily National Intelligencer (Hoban's report, December 23, 1819), January 3, 1820, p. 3. Library of Congress, Chronicling America. See the page - 1820NewspaperMoney voted
For finishing the President's house, $13,174.66, to cover expenditure beyond the 1818–19 grant.
Edwardsville Spectator (Act of February 10, 1820), March 21, 1820, p. 1. Library of Congress, Chronicling America. See the page - 1820NewspaperRepairs and improvements
Repairs in the President's house, $1,100.
Richmond Enquirer (acts of 1820), May 30, 1820, p. 1. Library of Congress, Chronicling America. See the page - 1823NewspaperBuilding progress
The south portico, six Ionic columns with entablature and balustrade, is completed; ceiling finished, roof covered with copper, the principal floor laid with Seneca stone. Cost $11,550.34.
Rhode-Island American (Hoban's report), December 26, 1823, p. 2. Library of Congress, Chronicling America. See the page - 1824NewspaperRepairs and improvements
For graduating and improving the grounds around the President's House, $2,000 (Senate amendment, receded).
Daily National Intelligencer, March 31, 1824, p. 3. Library of Congress, Chronicling America. See the page
2 · Supply
What was bought, stage by stage
Entries in the archive records about each kind of supply, for each stage of the work. The darker the square, the more entries.
| Stage | Stone | Brick | Lime, sand, plaster | Timber and plank | Metal | Slate and roofing | Glass and paint | Haulage | Provisions |
|---|---|---|---|---|---|---|---|---|---|
| Foundations and walls1792–1795 | 43 | 14 | 47 | 29 | 22 | – | 1 | 22 | 38 |
| Walls, roof and shell1796–1797 | 64 | 47 | 53 | 59 | 49 | 16 | 3 | 47 | 45 |
| Interior finishing1798–1800 | 9 | 20 | 26 | 29 | 32 | 40 | – | 7 | 6 |
| Lived in1801–1813 | 8 | – | – | – | 4 | 2 | 1 | – | 1 |
| Burned1814 | – | – | – | 1 | – | – | – | – | – |
| Rebuilt after the fire1815–1817 | 4 | 3 | 5 | 30 | 5 | – | – | – | – |
Stone was the work of 1792 to 1797, slate and metal of the roofing in 1798, and timber of the rebuilding in 1815. Haulage is carting stone, lime, timber and brick to the site; provisions are the pork, beef, meal and bread bought to feed the hands.
Prices, as written in the records
| Year | Item | As written | In plain terms | Source |
|---|---|---|---|---|
| 1795 | Brick | five Dollars & fifty Cents pr M | $5.50 a thousand bricks | John Mitchell to the Commissioners, December 1, 1795. RG 42, Entry 17, vol. 1, author's photograph 20230425_095914, National Archives, Washington, D.C. |
| 1795 | Pork for the workmen | 200 Bbls of Pork, at 15 $ per Bbl | $15 a barrel | John Mitchell, December 1, 1795. RG 42, Entry 17, vol. 1, author's photograph 20230425_095914, National Archives, Washington, D.C. |
| 1797 | Pork and beef | Pork @ $16 p Bbl & Beef @ $13 p Bbl | $16 and $13 a barrel | Proposal of Middleton Belt, October 13, 1797. RG 42, Entry 17, vol. 1, author's photograph 20230425_100538, National Archives, Washington, D.C. |
| 1797 | Stone lime | thirty six bushels of stone lime for use of the Presidents House @ 4/ | 4 shillings a bushel | Receipt of John Reed, April 8, 1797. RG 217, author's photograph 20191113_143622, National Archives, Washington, D.C. |
| 1797 | Window glass | 480 Squares of Glass 18 by 27 at p foot — 2.0 — 168.0.0 | 2 shillings a foot | Hoban's estimate, November 20, 1797. RG 42, Entry 17, vol. 1, author's photograph 20230425_100641, National Archives, Washington, D.C. |
| 1797 | Slating | Draising the slates and Covering six Dollars per / Square | $6 for each 100 square feet of roof | Proposal of Francis John Zeigler, November 29, 1797. RG 42, Entry 17, vol. 1, author's photograph 20230425_100819, National Archives, Washington, D.C. |
| 1799 | Plastering | To 1285 Yards of Plastering contained in Ceilings @ 1.6 pr — £ 96.7.6 | 1s 6d a square yard | Hoban's estimate, September 10, 1799. RG 42, Entry 17, vol. 1, author's photograph 20230425_101609, National Archives, Washington, D.C. |
| 1799 | Lime | 1406 Bushels of Lime — @ 3.0 — 210.18.0 | 3 shillings a bushel | Hoban's estimate, September 10, 1799. RG 42, Entry 17, vol. 1, author's photograph 20230425_101609, National Archives, Washington, D.C. |
| 1799 | Plaster of Paris | To 30 Tons of Plaster of Paris — @ 15 $ pr Ton — £ 168.15.0 | $15 a ton | Hoban's estimate, September 10, 1799. RG 42, Entry 17, vol. 1, author's photograph 20230425_101609, National Archives, Washington, D.C. |
| 1799 | Elliptic room cornice | 120 feet run, girt ft in 1.8 Measuring 250 feet @ 7.6 £ 93.15.0 | 7s 6d a foot of cornice, measured with its girt | Hoban's estimate, September 10, 1799. RG 42, Entry 17, vol. 1, author's photograph 20230425_101517, National Archives, Washington, D.C. |
| 1815 | Scantling for the new floors | To 84011 feet Scantling, reduced at $25 pr. M — $2100 | $25 a thousand feet | Hoban's bill, May 31, 1815. RG 42, Entry 17, vol. 1, author's photograph 20230425_102802, National Archives, Washington, D.C. |
| 1815 | Stone hearths and sills | Stone Hearth 14.40 per hearth … Stone Window Stools 4.50 per stool | $14.40 a hearth, $4.50 a window sill | Proposal of Peter Morte, April 11, 1815. RG 42, Entry 17, vol. 1, author's photograph 20230425_102558, National Archives, Washington, D.C. |
The Commissioners priced work in Maryland pounds, shillings and pence (12 pence to the shilling, 20 shillings to the pound) and paid in dollars. "M" is a thousand; "@ 1.6" is 1 shilling 6 pence; a square of slate is 100 square feet.
Suppliers named most often
- John T. Boucher29 entriesfirewood supplier, timber supplier
- John Dunbar14 entriesstone supplier
- John Mitchell13 entriesbrickmaker, provisions supplier
- Geo. Frank12 entriesprovisions supplier
- George Kliber11 entriesbaker
- George Blagden10 entriesstone supplier
3 · Money
What it cost
Money voted by Congress for the house
- 1807
Repairs and improvements of the house and groundsAct of Congress, New Hampshire Gazette, July 21, 1807, p. 1. Library of Congress, Chronicling America.
- 1810
Repairs to the house and officesAct of Congress, Virginia Argus, May 29, 1810, p. 1. Library of Congress, Chronicling America.
- 1818
Finishing $15,214; offices $7,000; furnishing $20,000 and a $10,000 deficiencyAct of Congress, Daily National Intelligencer, April 7, 1818, p. 3. Library of Congress, Chronicling America.
- 1820
Finishing deficiency $13,174.66; repairs $1,100Edwardsville Spectator, March 21, 1820, p. 1; Richmond Enquirer, May 30, 1820, p. 1. Library of Congress, Chronicling America.
From the acts of Congress as printed in the newspapers. One 1818 reprint reads sixteen thousand two hundred and fourteen for the finishing; the Intelligencer's $15,214 is used here. In 1824 the Senate proposed $2,000 for the grounds and then gave it up, so it is not counted.
4 · Labor
Who did the work
Trades named in the records
How many entries use each trade, counted in the clerks' own words in the Commissioners' records and the Treasury accounts.
- Carter, cartage
- Hired enslaved men ("Negro hire")
- Labourer
- Bricklayer
- Smith, blacksmith
- Sawyer
- Plasterer (plaisterer)
- Painter, glazier
- Slater
- Joiner (joyner)
- Carpenter
- Carver
- Overseer
- Stone cutter
- Bell hanger
- Mason
Pay, as written
| Year | Who | As written | In plain terms | Source |
|---|---|---|---|---|
| 1795 | A workman named Long, who signed by mark | 3s 2d for two Days work at President's House per Mr Mudd's roll for November | 1s 7d a day | Receipt, January 2, 1795. RG 217, author's photograph 20191112_102957. National Archives, Washington, D.C. |
| 1795 | Stone cutters, carvers and bricklayers | By President's House paid Roll of Stone Cutters, Stone Carvers & Brick Layers 1105.27 | One pay roll for the three trades, $1,105.27 | RG 42 account book, July 6, 1795 (Entry 14, f. 18), author's photograph 20190301_131326. National Archives, Washington, D.C. |
| 1796 | James Hoban, architect | By President's House for a quarterly Salary to 1st April 350.00 | $350 a quarter, $1,400 a year | RG 42 account book, May 14, 1796, author's photograph 9709. National Archives, Washington, D.C. |
| 1801 | Bell hanger from Philadelphia | at 4 Dolls pr Day for time & Expences | $4 a day | Geo. Hodderly's estimate, March 17, 1801. RG 42, Entry 17, vol. 1, author's photograph 20230425_101926. National Archives, Washington, D.C. |
Civic Atlas · Federal City
The records of the Commissioners who laid out and built the federal city, cited to the archives that hold the originals.
Back to Federal CityCounts are from the records read so far and will grow as more volumes are read. Every figure names the record it comes from; originals are held by the National Archives (Record Groups 42 and 217) and the newspapers by the Library of Congress, Chronicling America.